Earthworks calculator online

Calculate earthworks online. Enter the required dimensions and parameters to estimate quantities and key values.

DOC_REF // CALC-EARTHWORKS

Input data

Enter the value using the units shown. Check the measurements before calculating.
excavation Type

Result Excavation Volume0 m³
Result Soil Volume0 m³
Result Swell Factor1.30

Results are estimates. Verify all values against applicable standards and consult a qualified professional before construction.

01 / Calculation method

Earthworks volume estimate

Earthworks are an initial and critical stage of construction. This calculator estimates the geometric volume of soil to be excavated and the resulting loose soil volume for haulage, stockpiling, or backfill. It supports five common excavation types: trenches and pits with either vertical sides or sloped sides.

Excavation geometry formulas VV

The geometric volume VV in m³ is calculated for the selected shape as follows.

1. Trench with vertical sides

For a rectangular trench with vertical walls, treat the excavation as a rectangular prism:

V=a⋅H⋅LV = a \cdot H \cdot L

where aa is trench width in m, HH is trench depth in m, and LL is trench length in m.

2. Trench with slopes on both sides

In unstable or loose soils, trench walls are sloped. The cross-section is a trapezoid:

V=a1+a22⋅H⋅LV = \frac{a_1 + a_2}{2} \cdot H \cdot L

where a1a_1 is bottom width, a2a_2 is top width at ground level, HH is depth, and LL is trench length, all in meters.

3. Circular pit with sloped sides

Circular pits, for example for septic tanks, wells, or round supports, are calculated as a truncated cone:

V=π⋅H12⋅(d12+d1⋅d2+d22)V = \frac{\pi \cdot H}{12} \cdot \left(d_1^2 + d_1 \cdot d_2 + d_2^2\right)

where d1d_1 is the bottom diameter, d2d_2 is the top diameter, and HH is pit depth, in meters.

4. Rectangular pit without slopes

For a pit with vertical sides, volume is that of a rectangular prism:

V=A⋅B⋅HV = A \cdot B \cdot H

where AA and BB are pit length and width at the top/base in meters, and HH is excavation depth.

5. Rectangular pit sloped on all four sides

A pit sloped on all sides forms a truncated pyramid (prismoid). Calculate it from the bottom and top areas:

V=H3⋅(S1+S2+S1⋅S2)V = \frac{H}{3} \cdot \left(S_1 + S_2 + \sqrt{S_1 \cdot S_2}\right)

The base areas are:

S1=A1⋅B1S_1 = A_1 \cdot B_1

S2=A2⋅B2S_2 = A_2 \cdot B_2

where A1A_1, B1B_1 are bottom length and width; A2A_2, B2B_2 are top length and width; and HH is excavation depth, all in meters.

Loose excavated soil volume VbV_b

Once removed from undisturbed ground, soil structure is disturbed, density falls, and volume increases. The volume to haul away or spread on site is estimated as:

Vb=V⋅kV_b = V \cdot k

where VV is excavation volume in the ground, kk is the dimensionless initial bulking factor, and VbV_b is loose soil volume in m³.

Typical bulking factors by soil type are:

  • Loose soil or backfill: k=1.00k = 1.00
  • Dry sand: k=1.10k = 1.10
  • Damp sand: k=1.20k = 1.20
  • Sandy loam or loam: k=1.30k = 1.30
  • Dense clay: k=1.40k = 1.40

Geotechnical verification and safety standards

Excavation design and slope steepness must meet construction and safety requirements to prevent wall collapse. European engineering practice references:

  1. EN 1997-1 (Eurocode 7): Geotechnical design — General rules. It sets principles for slopes, retaining structures, and earthworks with regard to bearing capacity and soil limit states.
  2. EN 1997-2 (Eurocode 7): Ground investigation and testing. It supports field and laboratory determination of soil properties, including moisture, density, and internal friction angle, which affect allowable slope angle and bulking factor.
  3. Occupational safety rules for earthworks, which require shoring or sloped sides when excavation depth exceeds the limit for unsupported soil (typically more than 1–1.5 m, depending on the soil).

02 / Frequently asked questions

Why is “excavated soil volume” greater than “excavation volume”?

Excavation volume VV is the geometric volume of the hole or trench in undisturbed ground. When soil is dug by machine or by hand, particles separate and air voids increase. The resulting loose volume is estimated as Vb=V⋅kV_b = V \cdot k, where bulking factor kk is almost always greater than 1.001.00.

For sloped sides, should I enter the top dimensions or the base dimensions?

Enter both. A sloped trench uses a bottom width a1a_1 and top width a2a_2, and volume is calculated using the average width. A rectangular excavation with four sloped sides uses base dimensions A1A_1, B1B_1 and top dimensions A2A_2, B2B_2 because it forms a truncated pyramid. An incorrect value for any of these dimensions can cause a significant error.

How accurate is an excavation or trench volume estimate?

Accuracy depends on how closely the actual excavation matches the ideal geometric model. Wall deviations, uneven bottoms, sloughing at the slope edge, and local widening for formwork, sand bedding, or utilities all affect the result. Allow about 5–10% for these factors when planning work and purchasing materials.

Which soil bulking factor kk should I use for an estimate or haulage plan?

Typical reference values are k=1.10k = 1.10–1.201.20 for dry and damp sand, k=1.30k = 1.30 for sandy loam and loam, and k=1.40k = 1.40 for dense clay. For a formal estimate, select the value from applicable tables, such as national estimating standards or EN 1997-2, based on the actual soil type, density, moisture, and excavation method.

Can this calculation determine backfill volume?

Geometrically, backfill volume is close to excavation volume VV, but in practice subtract the volume of structures in the excavation, such as a concrete foundation, waterproofing, sand bedding, and wells. Backfill material estimates must also account for the required compaction using a residual bulking factor.